Two EcoCoolers were installed as part of a balanced ventilation system for a server room at Kings House, Bedworth to cover a 30KW Load.

The server room was being cooled by three existing CRACs (Conventional Computer Room Air Conditioners).  EcoCooling was chosen as a solution to reduce the electricity costs and associated carbon footprint.

The graph below shows the temperature performance achieved.
(100% compliance with ASHRAE 18°C to 27°C)

evaporative cooling chart - cooling the UPS room

 


CRAC


ECOCOOLING

SAVING
Annual KWhr
150,000
14,000
136,000
Cost
18,000
1,,680
16,320
Carbon Kg
80,500
7,500
73,000
cooling the UPS room at Warwick Council with evaporative cooling from ecocooling

 

 

Two evaporative cooling units were used in the server room as part of a balanced ventilation scheme.  The existing CRACs were retained as a backup. 

Since commissioning the CRACs have not been used

 

 

 

 

 